  • Planning PTP links

Planning PTP linksΒΆ

The goal of PTP link planning is to ensure that each direction of the link will perform to an acceptable level, measured by the Throughput and Availability values in the Performance Summary section of the Link Page. To allow LINKPlanner to predict Throughput and Availability, the planner must enter the variables that affect link performance, such as: band, region, equipment, antenna, height, terrain, obstructions and reflection.

To achieve this goal, follow this process:

  1. Start the application and set options. See Starting the Application.

  2. Build a project to model a PTP link (or network). See Projects.

  3. Enter details of all sites in the project. See Sites.

  4. Define the links between sites. See Links.

  5. Confirm that the link will perform to an acceptable level, measured by the Throughput and Availability values in the Performance Summary section of the Link Page.

  6. Export and report project, site and link data. See Exporting and Reporting

  • Links
    • Creating PTP Links
    • Displaying PTP Links
      • Deleting Links
      • Viewing & saving the list in MS Excel
  • Link Page
    • Link Description and Equipment
      • Link Description
      • Equipment (unlicensed bands)
      • Equipment (licensed bands)
      • Product Configuration (unlicensed bands)
      • Product Configuration (licensed bands)
    • Profile
    • Configuration at Each End
      • Licensed bands
    • Performance Summary
      • Performance to each Site
      • Operating Conditions
      • Link Summary
        • Performance Summary when TDM is selected
        • Link Summary additional information for 60 GHz cnWave, PTP 820 or PTP 850
    • Performance Details
      • Common Details
      • Performance to each end
    • Bill of Materials for Link
      • Viewing & saving the link BOM file in MS Excel
      • Power from switch
  • Advanced Features
    • Optimizing E1 or T1 Latency
    • Setting Diversity
      • Space Diversity
        • Reflections over Water
        • Multipath Reflections
      • Configuring Spatial Diversity in LINKPlanner
        • PTP 670
      • Height Clearance
    • Setting 2+0 Single Antenna
      • 2+0 Equipment Configuration
      • 2+0 Configuration at Each End
      • 2+0 Bill of Materials
      • 2+0 Performance Summary
      • 2+0 Reports
    • Setting Hot Standby Protection (1+1)
      • Hot Standby Configuration at Each End
      • Hot Standby Bill of Materials
      • Hot Standby Performance Summary
      • Hot Standby Reports
        • Proposal Report
        • Installation Report

Table of Contents

  • List of Figures
  • About This User Guide
  • Getting started
  • Using LINKPlanner
  • Planning PTP links
    • Links
    • Link Page
    • Advanced Features
  • Planning PMP networks
  • Background Information
  • Legal Notices
  • Changes to LINKPlanner
  • Glossary

Quick search

Navigation

  • index
  • next |
  • previous |
  • Cambium LINKPlanner Online Help (6.3.3) »
  • Planning PTP links
© Copyright 2025, Cambium Networks. Created using Sphinx 4.4.0.